The influence of historical conditions on time and cost of construction project - Publikacja - MOST Wiedzy

Wyszukiwarka

The influence of historical conditions on time and cost of construction project

Abstrakt

Conducting construction works in a building or in an area entered in the historic register is associated with the contracting authority's risk of incurring higher than planned costs of works, as well as delays in their implementation. In many cases, these deviations are completely independent of contracting authority and contractor. The aim of this article is to indicate the reasons for cost and time changes in the construction project, which is influenced by the historical conditions of the building site's location. In practice, the detailed considerations presented in the article may contribute to increasing the efficiency of spending public funds in the implementation of construction projects of a specific nature. Based on the selected example - reconstruction of the Old Pharmacy building located in the historic part of the old city of Gdańsk, the authors analyze and classify factors affecting the cost and time of construction works taking into account the historical conditions of the location of the facility.

Cytowania

  • 0

    CrossRef

  • 0

    Web of Science

  • 0

    Scopus

Cytuj jako

Pełna treść

pobierz publikację
pobrano 38 razy
Wersja publikacji
Accepted albo Published Version
Licencja
Copyright (2018 The Authors)

Słowa kluczowe

Informacje szczegółowe

Kategoria:
Aktywność konferencyjna
Typ:
publikacja w wydawnictwie zbiorowym recenzowanym (także w materiałach konferencyjnych)
Tytuł wydania:
Proceedings of the Creative Construction Conference (2018) strony 679 - 686
Język:
angielski
Rok wydania:
2018
Opis bibliograficzny:
Apollo M., Grzyl B., Paweł J.: The influence of historical conditions on time and cost of construction project// Proceedings of the Creative Construction Conference (2018)/ ed. Miroslaw J. Skibniewski & Miklos Hajdu : , 2018, s.679-686
DOI:
Cyfrowy identyfikator dokumentu elektronicznego (otwiera się w nowej karcie) 10.3311/ccc2018-090
Bibliografia: test
  1. H. Anysz, M. Książek, Wpływ opóźnień w realizacji kontraktu budowlanego na wzrost kosztów wykonawcy, in: Teoretyczne Podstawy Budownictwa, v. 2, Oficyna Wydawnicza Politechniki Warszawskiej, 2012.
  2. K. Ullah, A. H. Abdullah, S. Nagapan, S. Suhoo, M. S. Khan, Theoretical framework of the causes of construction time and cost overruns, IOP Conf. Ser. Mater. Sci. Eng. 271 (2017). otwiera się w nowej karcie
  3. A. Senouci, A. Ismail, N. Eldin, Time Delay and Cost Overrun in Qatari Public Construction Projects, Procedia Eng. 164 (2016) 368-375. otwiera się w nowej karcie
  4. Al Hammadi S., Nawab M. S., Study of Delay Factors in Construction Projects, Int. Adv. Res. J. Sci. Eng. Technol. 3 (2016) 87-93. otwiera się w nowej karcie
  5. M. Głuszak, A. Leśniak, Construction Delays in Clients Opinion -Multivariate Statistical Analysis, Procedia Eng. 123 (2015) 182-189. otwiera się w nowej karcie
  6. H. Anysz, A. Zbiciak, Przyczyny powstawania opóźnień w realizacji kontraktów budowlanych -analiza wstępnych wyników badania ankietowego, Autobusy 14 (2013) 963-972. otwiera się w nowej karcie
  7. A. Abderisak, P.E. Josephson, G. Lindahl, Aggregation of factors causing cost overruns and time delays in large public construction projects: Trends and implications, Eng. Constr. Archit. Manag. 24/3 (2017) 393-406.
  8. G. Niazi, N. Painting, Significant Factors Causing Cost Overruns in the Construction Industry in Afghanistan, Proc. Eng. 182 (2017) 510-517. otwiera się w nowej karcie
  9. A. Abderisak, P.E. Josephson, G. Lindahl, Implications of Cost Overruns and Time Delays on Major Public Construction Projects, in: Proceedings of the 19th International Symposium on Advancement of Construction Management and Real Estate (2015).
  10. N. Al-Hazim, Z. A. Salem, H. Ahmad, Delay and Cost Overrun in Infrastructure Projects in Jordan, Procedia Eng. 182 (2017) 18-24. otwiera się w nowej karcie
  11. S. Lindhard, S. Wandahl, Exploration of the reasons for delays in construction, Int. J. Constr. Manag. 14 (2014) 47-57. otwiera się w nowej karcie
  12. G. Polat, F. Okay, E. Eray, Factors Affecting Cost Overruns in Micro-scaled Construction Companies, Procedia Eng. 85 (2014) 428-435. otwiera się w nowej karcie
  13. B. Flyvbjerg, M.K. Holm, How common and how large are cost overruns in transport infrastructure projects?, Transp. Rev. 23 (2003) 71-88. [14] World Bank (2012), Construction Sector Transparency Program Goes Global [Online]: http://www.worldbank.org/en/news/feature/2012/11/08/construction-sector-transparency-program-goes-global. otwiera się w nowej karcie
  14. A. Leśniak, E. Plebankiewicz, Opóźnienia w robotach budowlanych, Zesz. Nauk. WSOWL 3/157 (2010).
  15. D. Kowalski, B. Grzyl, A. Kristowski, The Cost Analysis of Corrosion Protection Solutions for Steel Components in Terms of the Object Life Cycle Cost, Civ. Environ. Eng. Rep. 26/3 (2017) 5-13. otwiera się w nowej karcie
  16. M. W. Kembłowski, B. Grzyl, A. Kristowski, A. Siemaszko, Risk Modelling with Bayesian Networks-Case Study: Construction of Tunnel under the Dead Vistula River in Gdansk, Procedia Eng. 196 (2017) 585-591. otwiera się w nowej karcie
  17. B. Grzyl, A. Kristowski, K. Jamroz, A. Gobis, Methods of estimating the cost of traffic safety equipment's life cycle, MATEC Web Conf. EDP Sci. 122/ 02003 (2017). otwiera się w nowej karcie
  18. H. Anysz, T. Benedysiuk, Wpływ warunków miejskich na harmonogram budowy na przykładzie budowy obiektu biurowego, Logistyka 6 (2014) 1488-1495.
  19. A. Bortkiewicz, A. Wańska, Wstępne badania historyczno-konserwatorskie budynku Starej Apteki w Gdańsku. Gdańsk (2015).
  20. Ustawa z dnia 23 lipca 2003 r. o ochronie zabytków i opiece nad zabytkami (Dz.U nr 162 poz. 1568) (2003). otwiera się w nowej karcie
  21. The decision of the Provincial Pomeranian Conservator of Monuments No. ZN.5142.744.2017.AK of 06/10/2017. otwiera się w nowej karcie